SNGLT must now provide facemasks, soap, sanitiser, disposable
towel, disinfectant wipes, and a myriad of other Covid-19 associated items
simply to pursue the day to day work. Can you help with the costs?
Please donate as little as £5 when you can and as often as
you can using the "Donate" button
.
The equal lever of the Gresley conjugated gear has new bushes and is shown
on the machine after being bored out.
Photograph: Richard Swales
1 January 2020 |
The Cartazzi "wedges" have been skimmed by one of our volunteers
to restore the correct geometry.
Photograph: Richard Swales
9 January 2020 |
The trailing Cartazzi horn liners are worn beyond further use. Here the right
side one is being carefully removed.
Photograph: Richard Swales
9 January 2020 |
The keyways in the coupling and connecting rods are being carefully dressed
to remove wear and to ensure security of the key when the bushes are pressed in.
Photograph: Richard Swales
9 January 2020 |
The new steam pipe casting have been delivered and await transporting to
contractors for machining.
Photograph: Richard Swales
9 January 2020 |
The middle gudgeon pin before grinding has to be fitted with a plug drilled
with a centre hole so that the pin can be rotated about its cemntre accurately.
The plug is fitted at the large end.
Photograph: Darrin Crone
9 January 2020 |
The boiler lagging is now being fitted.
Photograph: Ken Woods
14 January 2020 |
The tender filler space is being painted ready to accept the air tanks. Here
shown in undercoat.
Photograph: Peter Brackstone
15 January 2020 |
The new valve guide casting is carefully positioned on the valve chest cover
before being drilled for its securing bolts.
Photograph: Richard Swales
16 January 2020 |
The crinoline that supports the streamline casing is being repaired and
painted before fitting.
Photograph: Richard Swales
18 January 2020 |
The air brake tanks have been hydraulically tested and passed by the insurance company.
Photograph: Darrin Crone
21 January 2020 |
The crinolines are prepared for fitting.
Photograph: Richard Swales
23 January 2020 |
Insulating the boiler. The insulation is retained with chicken wire.
Photograph: Richard Swales
23 January 2020 |
Two of the gudgeon pins after return from the grinders.
Photograph: Richard Swales
23 January 2020 |
All the coupling rod and outside big end bushes have now had keys made and
fitted, and the oiling felts fitted.
Photograph: Richard Swales
23 January 2020 |
The knuckle pins that join the coupling rods together have tapers machined to
provide best fit in the rods.
Photograph: Richard Swales
23 January 2020 |
The valve guides are mounted on the valve covers and are examined for their condition.
Photograph: Richard Swales
28 January 2020 |
One of the valve guides has been replaced by a new casting. It is being fitted to its
valve cover.
Photograph: Richard Swales
28 January 2020 |
All the cylinder relief valves have now been successfully tested at their set blow off
pressure. A lot of work has gone in to recovering some of these valves.
Photograph: Richard Swales
28 January 2020 |
All the crinoline sections, in order of fitting are in front of the loco being prepared.
Photograph: Trevor Camp / SNGLT
28 January 2020 |
The key ways in the rods show wear so these are dressed. The new keys fitted to the bushes locate in here.
Photograph: Richard Swales
30 January 2020 |
The backhead cladding is fitted. It can be seen where the numerous large sections
were previously cut out for repairs. These have been welded in place.
Photograph: Peter Brackstone
5 February 2020 |
The main boiler cladding after a preliminary clean. It is made up of original
sections, patches and newer material.
Photograph: Peter Brackstone
11 February 2020 |
More of the main boiler cladding showing the condition of some of the sections.
Photograph: Peter Brackstone
11 February 2020 |
We had a visit from twp Chelsea Pensioners.
Photograph: Tony Oldfield
12 February 2020 |
The Cartazzi overhaul is well under way. The bronze slide have been skimmed
to return them to the correct shape. Both are marked as being from 4464 Bittern,
the Left previously marked as being on V2 4788 (60817).
Photograph: Darrin Crone
12 February 2020 |
The trailing crossheads have been machined to remove all their whitemetal and
to true them up. The crosshead on the milling machine located on the valve
spindle socket.
Photograph: Richard Swales
12 February 2020 |
The loco now carries a complex electrical system. Here some of the wiring is
reinstalled after new conduit was run in below the cab floor.
Photograph: Richard Swales
13 February 2020 |
One of the coupling rod bushes about to be pressed in.
Photograph: Richard Swales
20 February 2020 |
One of the coupling rod bushes being pressed in, aligned by a close fitting
key.
Photograph: Trevor Camp / SNGLT
20 February 2020 |
The old valve guide that was unacceptably out of position is machined to
correct its alignment.
Photograph: Richard Swales
21 February 2020 |
The reverser column is refitted now the backhead cladding is in place and
painted.
Photograph: Peter Brackstone
27 February 2020 |
Not mentioned in the report but there's plenty of activity on more minor
components. Here the cover for the tender gangway top spring is being painted
before fitting.
Photograph: Peter Brackstone
27 February 2020 |
New tender streamlining steel in position.
Photograph: Richard Swales
27 February 2020 |
The streamlined casing shows corrosion along the sides and bottom edges. New
steel is welded in.
Photograph: Darrin Crone
3 March 2020 |
Four Cartazzi Spenser spring bottom plates are required we are using two old
and two new.
Photograph: Darrin Crone
4 March 2020 |
The lower cod's mouth door assembly being fitted after riveting and painting.
Photograph: Peter Brackstone
5 March 2020 |
To work on the boiler safely we have had to invest in access equipment. It is
all checked weekly following a controlled procedure.
Photograph: Richard Swales
5 March 2020 |
The battery box is being fabricated.
Photograph: Richard Swales
5 March 2020 |
The tender coal door catch after refurbishment.
Photograph: Darin Crone
8 March 2020 |
The back corner cladding pieces have been repaired, fitted and painted in undercoat.
Photograph: Peter Brackstone
11 March 2020 |
The tender gangway floorplate is in place.
Photograph: Richard Swales
12 March 2020 |
The new Cartazzi bronze bearing casting, now being machined.
Photograph: Richard Swales
12 March 2020 |
The projections from the back of the valve chest covers have to be the
correct length to located against the valve liners.
Photograph: Richard Swales
14 March 2020 |
One of the coupling rod oiling rings having it's oil retaining holes de-burred.
Photograph: Darrin Crone
16 March 2020 |
The last cast iron steam pipe to be machined at contractors. The position of
the datum for the holes to be drilled in the flange is being discussed.
Photograph: Darrin Crone
17 March 2020 |
The wedges for the lower tender vestibule support brackets being skimmed to restore their shape.
Photograph: Darrin Crone
17 March 2020 |
The left knuckle pin is fitted to the coupling rod.
Photograph: Darrin Crone
19 March 2020 |
The right leading oiling ring is pressed onto the bearing that projects
through the rod and into a recess in the rods.
Photograph: Richard Swales
20 March 2020 |
The coal door frame has been partially riveted. The rivets being ground flush.
The original small section of roof over the corridor is refurbished and fitted .
Photograph: Richard Swales
20 March 2020 |
The new valve guide bolts have the hex head machined on an Elliott milling
machine, indexed with a Fritz Werner dividing head.
Photograph: Darrin Crone
27 March 2020 |
The new valve guide bolts have their overall lengths marked off on a flat
surface with a vernier height gauge. 29 March 2020
Photograph: Darrin Crone
29 March 2020 |
As the bolt heads won't pass through the headstock of the Colchester
Student lathe, the ends have to be supported in a three point steady then
machined to length.
Photograph: Darrin Crone
29 March 2020 |
The completed bolts with pin holes drilled, next to the old bolts.
Photograph: Darrin Crone
30 March 2020 |
One of the knuckle pins on a Bridgeport milling machine having the cotter machined.
Photograph: Tony Bickerstaff
30 March 2020 |
The keyway slot of the left knuckle pin is machined by indexing round by 90
degrees with a substantial rotary table.
Photograph: Tony Bickerstaff
30 March 2020 |
Lubricator drive crank components
Photograph: SNGLT Engineering Team
|
Lubricator drive crank
Photograph: SNGLT Engineering Team
|
TPWS bell
Photograph: SNGLT Engineering Team
|
TLED spotlight unit
Photograph: SNGLT Engineering Team
|
New TPWS and OTMR battery box
Photograph: SNGLT Engineering Team
|
Cartazzi bearing casting
Photograph: SNGLT Engineering Team
|
Cartazzi bearing casting
Photograph: SNGLT Engineering Team
|
The new tender battery enclosure.
Photograph: Richard Hawkhead
31 May 2020 |
The tender water gauge valve and new stainless steel adaptor
Photograph: Peter Slater
8 June 2020 |
The AWS/TPWS sunflower unit used as a warning indicator and to acknowledge
signals
Photograph: Mike Page
11 Jun 2020 |
The middle big end test bush made to high accuracy and will be used to ensure
the middle big end bearing is held securely in the rod.
Photograph: D Holmes
14 July 2020 |
One of the handbrake link side plates being machined with a radius where the section thickness changes
Photograph: Darrin Crone
15 July 2020 |
The handbrake side links and centre block trial assembled on dowel pins ready
for final welding
Photograph: Darrin Crone
7 August 2020 |
One of the new tender vestibule support rod packing pieces has been machined
and is being drilled
Photograph: Darrin Cronw
8 August 2020 |
One of the new blast pipe caps being machined with the use of a rotary table
Photograph: Tony Bickerstaff
10 August 2020 |
Refurbished boiler pressure gauges.
Photograph: Darrin Crone
2 September 2020 |
The devil is in the detail, individually made smoke box studs with drawing
and material purchase order detail
Photograph: Darrin Crone
5 September 2020 |
The re-metalled and machined middle piston valve tail rod bush
Photograph: Darrin Crone
5 September 2020 |
The new and ex-service blast pipe caps, with a 7¼" gauge version
Photograph: Darrin Crone
6 September 2020 |
Two new nuts made for the coupled wheel spring hangers to replace
"odd" sized nuts. Now we only need one spanner to adjust the brakes
instead of having to remember the odd ones!
Photograph: Darrin Crone
27 September 2020 |
First day back in the workshop, our maximum permitted attendance is five. Our
last day before lockout we had 16. It's very quiet.
Photograph: Richard Swales
29 September 2020 |
We have set up our own "wash station" in the corner of the
workshop. All we need now is to get the hot tap to work,
Photograph: Darrin Crone
30 September 2020 |
The valve covers are fitted
Photograph: Richard Swales
1 October 2020 |
An old tender dragbox bush and the last new one ready to go in. I suppose it
was due a change.
Photograph: N Franklin
2 October 2020 |
Two of the 4 new bushes now fitted in the tender dragbox. The side or safety
link pins go through these bushes. The side links provide a backup connection
between loco and tender if the main drawbar fails.
Photograph: N Franklin
2 October 2020 |
Measurements have been taken of the Cartazzi horn gaps to enable liners to be
specified.
Photograph: Richard Swales
7 October 2020 |
With the valve cover on and the valve in place the offset dimensions can be
taken.
Photograph: Richard Swales
7 October 2020 |
The knuckle pin bushes are pressed in to the trailing coupling rods.
Photograph: Richard Swales
8 October 2020 |
The loco brake gear is laid out and the rebushed links pinned up to check fit
and dimensions taken for new pins.
Photograph: Darrin Crone
16 October 2020 |
One of the refurbished lower vestibule support assemblies fitted with the new
floorplate above.
Photograph: Darrin Crone
16 October 2020 |
The new tender side link pins that will go through the new bushes. The one
with the longer top goes through a longer hole in the cast iron balance weight.
It gives me something to hold on to for removal. br>
Photograph: Darrin Crone
18 October 2020 |
Riveting the coal door frame on to the front plates of the tende.
Photograph: Peter Brackstone
20 October 2020 |
An Engineering Team volunteer boring the new little end bushes.
Photograph: Richard Swales
20 October 2020 |
The right coupling rods are lifted on to the crankpins.
Photograph: Richard Swales
20 October 2020 |
The right coupling rods fitted and leading crankpin cap.
Photograph: Richard Swales
20 October 2020 |
The ends of the new Cartazzi hangers have been slotted and the undercuts at
the ends of the threaded section have been finished. br>
Photograph: Darrin Crone
23 October 2020 |
New brake pins freshly machined by a volunteer.
Photograph: Darrin Crone
23 October 2020 |
A white-metalled crosshead being machined in the home workshop of one of our
volunteers.
Photograph: Richard Swales
26 October 2020 |
The right combination lever fitted to the radius rod, the machined valve
crosshead in place on the valve spindle but not pinned in to the combination
lever.
Photograph: Richard Swales
29 October 2020 |
The middle cylinder steam pipes tried in place.
Photograph: Darrin Crone
4 November 2020 |
The left side combination lever fitted to radius rod and valve crosshead
being set up for mid gear position. br>
Photograph: Richard Swales
5 November 2020 |
New pipe end cones for the atomiser steam supply pipework.
Photograph: Darrin Crone
6 November 2020 |
The new cast iron steam pipes that are fastened to the tops of the cylinders
are fastened together and pressure tested.
Photograph: Darrin Crone
12 November 2020 |
The CME ponders on the valve head positions on the spindle.
Photograph: Tont Bickerstaffe
12 November 2020 |
One of the little end bushes during machining by one of our Engineering Team volunteers.
Photograph: Tont Bickerstaffe
12 November 2020 |
The handbrake link being machined in a volunteer's workshop. br>
Photograph: Richard Swales
17 November 2020 |
The steam supply pipe to the air pump is pressure tested before final fitting to the loco.
Photograph: Darrin Crone
17 November 2020 |
Not open to the public a view of the loco from the viewing gallery.
Photograph: Richard Swales
19 November 2020 |
Also seen from the public gallery, the tender.
Photograph: Richard Swales
19 November 2020 |
The new cast iron steam pipe in position with the ex-service steel pipe cut
to fit.
Photograph: Richard Swales
19 November 2020 |
The left lower combination lever and piston crosshead drop link pin holes are
compared for alignment during fitting of the union link. br>
Photograph: Richard Swales
20 November 2020 |
Once cut and with the end flanges in position the cuts in the pipe are
bridged to hold the pipes new shape.
Photograph: Richard Swales
20 November 2020 |
The right side valve gear assembly with union link fitted.
Photograph: Richard Swales
20 November 2020 |
The left union link being measured for twist.
Photograph: Richard Swales
24 November 2020 |
The new handbrake link machined by Engineering Team volunteers with the
ex-service behind.
Photograph: Richard Swales
27 November 2020 |
The coach has arrived at contractors for the overhaul of the underframes.
Photograph: Darrin Crone
2 December 2020 |
The new loco brakeshaft bearings during machining, with the same components
in model form for a 7¼" A4.
Photograph: Darrin Crone
3 December 2020 |
The new tender corridor canopy fitted. Original drawings were used to
fabricate this part.
Photograph: Richard Swales
4 December 2020 |
The two loco brakeshafts being rebushed.
Photograph: Richard Swales
4 December 2020 |
The little end bearings being slotted for their oiling felts.
Photograph: Tony Bickerstaffe
8 December 2020 |
One of the cast iron steam pipes being set up for drilling.
Photograph: Richard Swales
11 December 2020 |
The coach has been lifted for the underneath of the coach and bogies to be
thoroughly inspected.
Photograph: Richard Swales
16 December 2020 |
Everything needs painting, and work proceeds on a little end keyway.
Photograph: Richard Swales
18 December 2020 |
The ex-service cladding sheets with a new steel sheet being marked out and drilled.
Photograph: Richard Swales
18 December 2020 |
One of the middle big end bearing half castings having the mating surface
machined.
Photograph: Tony Bickerstaffe
21 December 2020 |
After the faces are machined they are tinned with solder.
Photograph: Tony Bickerstaffe
22 December 2020 |
After aligning the halves they are soldered together.
Photograph: Tony Bickerstaffe
22 December 2020 |
The new cladding sheet being welded. In front the middle trailing valve cover
waiting to be welded so that the end stop can be finished to the correct length.
Photograph: Richard Swales
22 December 2020 |
Santa's leading artisan elf popped in to help with some pipework on his
way to the North Pole.
Photograph: Richard Swales
22 December 2020 |
The middle big end bearing halves soldered ready to go for machining.
Photograph: Darrin Crone
23 December 2020 |
The new right leading boiler cladding panel in place.
Photograph: Darrin Crone
23 December 2020 |
The right leading brakeshaft bearing in position.
Photograph: Darrin Crone
23 December 2020 |
The leading left brakeshaft bearing housing is honed to remove taper and
improve circularity for the fitting of the bearing.
Photograph: Tony Bickerstaffe
23 December 2020 |
The little end bearings are keyed in to the connecting rods. New keys being
ground to size.
Photograph: Tony Bickerstaffe
30 December 2020 |
All photographs are copyright of the photographer named on the
larger version.