The flue tubes in the boiler at Llangollen are trimmed to length.
Photograph: Paul Aston
3 January 2019 |
The trailing left crank pin end is fitted with the crank for the speedo
drive. The gap between the crank and the face of the wheel will fix the length
of the bearing bush fitted to this crankpin.
Photograph: Darrin Crone
5 January 2019 |
The sidebearer on the left. The loco frames are resting on the top of the
bogie when moved off the wheeldrop. When levelled the gap appeared and was measured.
Photograph: Darrin Crone
5 January 2019 |
The outside draincock cross shaft has been fitted.
Photograph: Darrin Crone
5 January 2019 |
The governor that controls the air pump in its new location with new pipe
flanges ans pipework being installed.
Photograph: Darrin Crone
5 January 2019 |
The leading and trailing connecting rod bushes are now machined all over.
The larger bushes yet to do.
Photograph: Darrin Crone
5 January 2019 |
The sponsored horizontal hornstay bolts machined to dimensions ready to fit.
Photograph: Darrin Crone
5 January 2019 |
One of the tender brake hangers with the bushes and pins being examined.
Photograph: Darrin Crone
5 January 2019 |
At the rear of the tender old platework is cut out.
Photograph: Darrin Crone
15 January 2019 |
The front lamp irons are heavily worn and were put on the loco to get the
angles correct for the repair.
Photograph: Peter Brackstone
17 January 2019 |
Pins from the buckeye coupling and coupled axleboxes are inspected for
defects.
Photograph: Darrin Crone
17 January 2019 |
The top of the corridor connection at the back of the tender is supported by
square section rods that pass through these brackets with adjustable wedges.
Photograph: Darrin Crone
19 January 2019 |
The cast iron steam pipes that fasten on to the cylinder tops are measured
to ensure the new ones will be to the same dimensions.
Photograph: Richard Swales
19 January 2019 |
Some of the loco brake pull rods undergoing examination for defects.
Photograph: Darrin Crone
22 January 2019 |
Ian looks admiringly at his refurbished air cylinder brackets.
Photograph: Darrin Crone
23 January 2019 |
One of the loco brake pull rods is marked W1 at both ends. Could this be from the hush-hush?.
Photograph: Darrin Crone
23 January 2019 |
The water gauge or level indicator from the front of the tender.
Photograph: Peter Brackstone
26 January 2019 |
The vacuum reservoir tank is pressure tested to inspect for leaks.
Photograph: Darrin Crone
29 January 2019 |
The vacuum reservoir tank tested ok so was soon painted.
Photograph: Peter Brackstone
31 January 2019 |
The lower slidebars are now being fitted.
Photograph: Darrin Crone
6 February 2019 |
New plate has been welded in to the wasted section inside the corridor atthe rear of the tank.
Photograph: Darrin Crone
7 February 2019 |
The welding is now complete on the tender frames and has been prime painted.
Photograph: Peter Brackstone
7 February 2019 |
Painting of the tender frames is progressing. The frames are now white gloss
inside and the trailing dragbox is now painted in primer.
Photograph: Peter Brackstone
7 February 2019 |
New safety valves springs have now been delivered to York. A new valve next
to one of our old valves.
Photograph: Darrin Crone
10 February 2019 |
A new rivet has been put in one of the tender spring hanger brackets.
Luckily it didn't loosen its neighbours so these can be left as they are.
Photograph:
10 February 2019 |
The trailing dragbox is painted to undercoat. We will soon be able to
reassemble the trailing drawgear.
Photograph: Peter Brackstone
13 February 2019 |
The crankpin lengths are measured so that the length of the siderod bushes
can be specified.
Photograph: Richard Swales
14 February 2019 |
The leading crankpin bolts have been refurbished and are ready for fitting.
They rest on one of the caps that require further work to return them to
specification.
Photograph: Darrin Crone
16 February 2019 |
The vestibule lower supports are now having the weld added to rebuild them
machined back prior to fitting.
Photograph: Darrin Crone
16 February 2019 |
The tender rubbing block was refitted this week.
Photograph: Darrin Crone
16 February 2019 |
The safety valves are being assembled with new components.
Photograph: Darrin Crone
16 February 2019 |
One of the tender brake hangers is fitted with new bushes and one of the
reconditioned pins fitted.
Photograph: Darrin Crone
16 February 2019 |
With the wheelset in the wheeldrop pit the journals are cleaned and oiled to
receive the axleboxes.
Photograph: Trevor Camp/SNGLY
22 February 2019 |
Looking through the trailing horns of the loco frames an axlebox is lowered on to the journal.
Photograph: Trevor Camp/SNGLY
22 February 2019 |
The wheelset raised and entering the frames.
Photograph: Trevor Camp/SNGLY
22 February 2019 |
The wheels in place and the wheeldrop platform locked in the raised position.
Photograph: Trevor Camp/SNGLT
22 February 2019 |
The bogie is lowered to remove the loco sidebearers.
Photograph: Richard Swales
22 February 2019 |
The tender outside brake cylinder brackets ready for painting and fitting.
Photograph: Darrin Crone
23 February 2019 |
The trailing tender coupling is now partially assembled with all the rubber
springs in place.
Photograph: Darrin Crone
23 February 2019 |
The new air pump governor installation has received a coat of paint.
Photograph: Peter Brackstone
27 February 2019 |
The new copper firebox tubeplate with all the tubes fitted and beaded over.
Photograph: Peter Brackstone
28 February 2019 |
The flue tubes in the smokebox are now being expande.
Photograph: Richard Swales
28 February 2019 |
The new superheater elements at Llangollen.
Photograph: Richard Swales
28 February 2019 |
The rubbing block for the tender draw hook sits on the new shim all level.
Photograph: Darrin Crone
2 March 2019 |
The new horizontal hornstay bolts are being fitted and are being drilled through for pinning.
Photograph: Darrin Crone
2 March 2019 |
The hook is now in place on the tender and it's height being measured.
Photograph: Darrin Crone
2 March 2019 |
The driving axle axleboxes are currently being fitted.
Photograph: Richard Swales
7 March 2019 |
The tender drawhook height is being set. A new packing piece to set the
height is being machined after being fitted accurately in the pocket in the dragbox.
Photograph: Peter Brackstone
7 March 2019 |
The full hook assembly is now fitted to the tender and its correct height is
being set.
Photograph: Darrin Crone
9 March 2019 |
At the back of the tender the beading is re-secured and the vestibule top
arch flanges are fitted in place.
Photograph: Darrin Crone
9 March 2019 |
The corridor connection lower support rods have been weld repaired and
machined but will require further work.
Photograph: Darrin Crone
9 March 2019 |
Both the leading and trailing coupled wheel hornstays are now fully secured
with the publicly sponsored horizontal hornstay bolts.
Photograph: Darrin Crone
9 March 2019 |
The middle valve and its associated components have been brought together
and are being carefully examined and set up before refitting.
Photograph: Darrin Crone
9 March 2019 |
One of the valve crosshead guides. There are ten of these as we have valve
gear both in front and to the rear of the the valve chests.
Photograph: Darrin Crone
9 March 2019 |
The tender springs are loaded on to pallets ready for dispatch to
contractors for overhaul.
Photograph: Darrin Crone
12 March 2019 |
With welding complete at the front of the tender frames they can now be
painted. Here in undercoat.
Photograph: Peter Brackstone
13 March 2019 |
The top corner of the tender where new plate has been welded in, and bolts
securing the structure are ground so they are hidden when finished. Inside the
vestibule paint has been applied.
Photograph: Peter Brackstone
13 March 2019 |
The profile on the valve for the inside of the safety valve has been
reprofiled. The spigot fits in to the centre of the new bottom flange.
Photograph: Darrin Crone
16 March 2019 |
The upper rear brake hanger holes are being bored.
Photograph: Richard Swales
21 March 2019 |
The leading and trailing coupled wheel springs are now fitted.
Photograph: Peter Brackstone
27 March 2019 |
Another section of wasted tender has been cut out and will be replaced.
Photograph: Peter Brackstone
28 March 2019 |
The boiler is now the right way up and is now being filled with water.
Photograph: Richard Swales
29 March 2019 |
A view of the boring arrangement inside the tender dragbox. This end
supported by one of the old tender vacuum brake cylinder brackets.
Photograph: Richard Swales
4 April 2019 |
The last coupled axlebox is now fitted.
Photograph: Richard Swales
4 April 2019 |
The tender rear drawhook rubbing block now sets the hook to the correct
height.
Photograph: Richard Swales
4 April 2019 |
The tender vestibule arch fabrication in place. Being close to the top
beading makes it very difficult to fit.
Photograph: Darrin Crone
6 April 2019 |
The new vestibule arch piece is in place. The plate behind and below the top
edge beading has also been renewed at this overhaul.
Photograph: Peter Brackstone
11 April 2019 |
Another section of tender plate has been cut out for renewal.
Photograph: Peter Brackstone
11 April 2019 |
The new tender lower brake hanger pin next to the old. The new one has a
head as shown on the LNER drawing. Made by a volunteer member of the
Engineering Team.
Photograph: Darrin Crone
13 April 2019 |
The atomisers are mounted on temporary brackets so that pipework can be run
to them.
Photograph: Darrin Crone
13 April 2019 |
New slide bar shims are being precision ground.
Photograph: Darrin Crone
13 April 2019 |
A replacement safety valve cap (left) has been made at some time during
preservation. It fit was improved by machining the inner profile to match an
original.
Photograph: Darrin Crone
16 April 2019 |
The refurbished front lamp irons have been refitted.
Photograph: Darrin Crone
17 April 2019 |
The boiler full of water sits silently under hydraulic test.
Photograph: Darrin Crone
23 April 2019 |
The first sections of steel are being cut out of the tender front.
Photograph: Darrin Crone
1 May 2019 |
Our bronze side rod bushes in the process of manufacture. The internal
serrations will improve the key for the whitemetal that will be cast inside of
them.
Photograph: Darrin Crone
2 May 2019 |
We have drawings of the tender but it also needs to be carefully measured to
ensure the tender is still to drawing after such a long life.
Photograph: Richard Swales
2 May 2019 |
Our collection of boiler gauges are being refurbished and checked for accuracy.
Photograph: Andy Barwick
6 May 2019 |
Reaming of the right side tender horn stay holes to ensure a good fit for
the bolts.
Photograph: Richard Swales
9 May 2019 |
A gauge has been manufactured to ensure accurate finishing of the middle crank pin.
Photograph: Darrin Crone
11 May 2019 |
The big end of the inside connecting rod is adjusted and measured to find
the roundness for securing the bearing.
Photograph: Darrin Crone
11 May 2019 |
The tender brakeshaft is tried in position.
Photograph: Darrin Crone
11 May 2019 |
To get the blast pipe tops off the retaining studs had to be drilled out.
Photograph: Ken Woods
14 May 2019 |
The painting table in the workshop which has seen hundreds of parts painted.
Photograph: Ken Woods
14 May 2019 |
The new floorplate that will go inside the tender vestibule.
Photograph: Peter Brackstone
15 May 2019 |
The tender tank is now receiving filling and painting to remove signs of our
repairs.
Photograph: Peter Brackstone
16 May 2019 |
The right leading tender brass is being scraped to its journal.
Photograph: Darrin Crone
18 May 2019 |
The big end strap has been thoroughly examined by SNG, however due to its
criticality it will now be inspected by a certified 3rd party.
Photograph: Darrin Crone
18 May 2019 |
A strengthening beam has been welded across the front of the tender tank to
maintain its shape when more material is removed.
Photograph: Darrin Crone
18 May 2019 |
The tender brakeshaft is trial fitted.
Photograph: Peter Brackstone
29 May 2019 |
More steelwork is removed from the tender front P Brackstone.
Photograph: Peter Brackstone
30 May 2019 |
The boiler with a fire in it is drawn in to the open in the yard at Llangollen.
Photograph: Paul Aston
30 May 2019 |
A platform was built so that the top of the boiler can be accessed.
Photograph: Darrin Crone
31 May 2019 |
The leading tender wheelset has the axleboxes fitted and is ready for trial
fitting in the frames.
Photograph: Richard Swales
1 June 2019 |
The left refurbished tender vestibule support rod and housing are refitted
to allow the routing of the tender water filler pipes in the dragbox.
Photograph: Richard Swales
1 June 2019 |
The leading tender wheelset in place.
Photograph: Peter Brackstone
4 June 2019 |
The coal door frame refitted after removal of the tender front platework.
Photograph: Peter Brackstone
5 June 2019 |
Part of the scoop arrangement that will be refitted to the tender front.
Photograph: Peter Brackstone
5 June 2019 |
Making the back of the tender look like it was never repaired
Photograph: Ken Woods
6 June 2019 |
The tender brakeshaft has been tested, trial fitted and now painted.
Photograph: Richard Swales
13 June 2019 |
The dummy return crank is fitted on the crankpin square.
Photograph: Richard Swales
13 June 2019 |
The reversing assembly lifting arm with new pin coupled to the reverser reach rod.
Photograph: Darrin Crone
15 June 2019 |
Nearly all the cab piping and cab floor structure has been removed for
painting. The pipe team is not amused.
Photograph: Peter Brackstone
19 June 2019 |
The ashpan being lowered in to the frames.
Photograph: Ken Woods
19 June 2019 |
The ashpan in position.
Photograph: Trevor Camp / SNGLT
20 June 2019 |
The jig that will be used to set the return crank angle and length on our
new crankpins.
Photograph: Richard Swales
22 June 2019 |
At the front of the inside tender frames, air brake pipes and TPWS conduit
are terminated. The old TPWS junction box is fitted for sizing and will be replaced.
Photograph: Richard Swales
22 June 2019 |
The cab floor has been stripped out to allow the structure to be finish painted.
Photograph: Peter Brackstone
25 June 2019 |
Pallets loaded with tender springs return from refurbishment
Photograph: Peter Brackstone
25 June 2019 |
The coach stripped back to metal prior to skin repairs at the workshops of CTMS.
Photograph: Richard Swales
26 June 2019 |
The coach side that has been repaired.
Photograph: Richard Swales
26 June 2019 |
|
|
|
|