This week the front of the tender has been worked on. The needle gun, one of our favorite tools
is used on the front dragbox.
Photograph: Peter Brackstone.
4 July 2017 |
The fireman's side clack box casting we are to replace. I am willing to consider outrageous
financial offers for this unique artifact.
Photograph: Darrin Crone.
7 July 2017 |
At the works of K D Flavell the superheater header is welded vertically to a heavy steel beam to
ensure no distortion and making it easier to move during refurbishment.
Photograph: Darrin Crone
7 July 2017 |
Also at the works of K D Flavell the loco side bearers that stop excessive rolling of the loco
by contacting the bogie side bearers. One was cracked and this has now been repaired. However both
side bearers have been examined.
Photograph: Darrin Crone.
7 July 2017 |
The exhaust pipe from the air pump is now fitted.
Photograph: Peter Brackstone.
13 July 2017 |
The small ejector valve has had to be re-machined to remove a large steam cut from the valve
seat.
Photograph: Darrin Crone.
15 July 2017 |
The worn tapped holes in the footplate angles that the streamlining is fastened to are being
welded up. They will then be dressed and the holes remade.
Photograph: Darrin Crone.
15 July 2017 |
After cleaning and scraping the left hand water valve under the front of the tender.
Photograph: Darrin Crone.
15 July 2017 |
One of the side bearer plates added later in the life of the bogie. Two of the countersunk
screws had to be replaced as they were life expired. The new screws are made with a reduced section
just above the countersink so that when sufficient torque is applied the head it breaks off. The
centre sheared section will be ground down.
Photograph: Darrin Crone.
15 July 2017 |
The underside of the footplating has been finished in gloss paint. Not an easy or pleasant job
to paint over your head for hours, so well done to the Painting Team.
Photograph: Darrin Crone.
15 July 2017 |
The loco bogie side bearer brackets were returned to York this week. The right side was cracked
and this has been repaired.
Photograph: Darrin Crone.
15 July 2017 |
The bogie centre casting on the large horizontal borer in the works of K D Flavell having the
lower bearing faces skimmed.
Photograph: Darrin Crone.
17 July 201 |
The underside of the loco bogie stretcher was di-pen inspected this week. No faults were found.
In this view the leading right hand underside of the stretcher can be seen with the vertical row of
bolts that hold the front of the outside cylinder on to the frames.
Photograph: Darrin Crone.
18 July 2017 |
Overhaul webpage favourite, Alan Pitt, needle guns the inside of the front corner streamlining.
Photograph: Peter Brackstone.
18 July 2017 |
Dave Lee has been welding up worn threaded holes that secure the front streamlining. Here he
grinds excess weld from the front right hand footplate angle.
Photograph: Peter Brackstone.
19 July 2017 |
The coupled wheel and bogie axleboxes have now been delivered to Grosmont for re-metalling and
machining.
Photograph: Peter Brackstonee.
20 July 2017 |
Some of the components that make up the gravity sander operating mechanism. The parts have been
inspected for defects and will now be refurbished.
Photograph: Darrin Crone.
22 July 2017 |
The mud hole doors from 60007's boiler were in store at Grosmont having been removed from
the boiler when the loco came out of traffic in 2015. They have now been moved to York. They will
be cleaned up and sent to Llangollen for refurbishment and fitting to the boiler.
Photograph: Darrin Crone.
22 July 2017 |
The front buffer housings were were put back on the front bufferbeam this week.
Photograph: Darrin Crone.
22 July 2017 |
New rivets have been fitted to the leading brake cylinder loco stretcher. This is the right hand
side where three new rivets have been fitted. Similarly the left hand has required three new
rivets. By the appearance of the frames in this area this is a job that has been carried out a
number of times in the locos history.
Photograph: Darrin Crone.
22 July 2017 |
The regulator stuffing box faces have been re-machined and the pad that locates the regulator
rod pin machined to give the correct offset. The finish and fit is superb.
Photograph: Darrin Crone.
22 July 2017 |
New bolts have been fitted to the regulator support beam, one just visible in the photo. The
long regulator valve hanger bolts are laid on the valve with a cut off old bolt still in the
support beam to indicate its position, though the bolt is screwed in to the other side of the beam
when fitted.
Photograph: Darrin Crone.
22 July 2017 |
New bolts have been fitted to the joint between the saddle casting and the middle cylinder
casting, the culmination of a considerable amount of work in preparing the casting surfaces.
Photograph: Darrin Crone.
22 July 2017 |
A view inside the tender corridor looking through the window at the rear of the tender. The
original 1928 construction of the tender is evident by the riveting.
Photograph: Peter Brackstone.
25 July 2017 |
The front streamlining is trial fitted during the repair of the fastening holes and streamlined
panels.
Photograph: Peter Brackstone.
26 July 2017 |
The gravity sandbox studs are drilled on a jig to save time setting up for each stud.
Photograph: Bob Shearman.
27 July 2017 |
The driving wheelset at the works of the South Devon Railway. All repairs are complete and the
wheelset will be returned to York soon.
Photograph: Richard Swales.
27 July 2017 |
The leading bogie wheelset ready to return to York.
Photograph: Darrin Crone.
27 July 2017 |
The leading and trailing coupled wheelsets have all repairs completed, and as the rest of
60007's wheelsets, they have been subject to detailed inspection by SNG Engineers.
Photograph: Darrin Crone.
27 July 2017 |
The removed right hand driving crank pin, bearing number 26 as the wheelset was originally
fitted to Miles Beevor. It will be retained as a possible reference in the positioning and
fit of the existing valve gear crank to the new crank pin.
Photograph: Darrin Crone.
27 July 2017 |
The bore of the left hand combined brake shaft and spring bracket has been skimmed to repair the
surface.
Photograph: Richard Swales.
29 July 2017 |
Not mentioned in this weeks report but mentioned in previous reports, the new bogie side control
bolt to the right, has been fitted with a new key, the nut and cotter have been dressed to improve
their fit.
Photograph: Richard Swales.
29 July 2017 |
The new valve liners for the middle and right hand valve chest have been delivered to York from
contractors this week.
Photograph: Darrin Crone.
2 August 2017 |
The front coupling hook was refitted to the repainted bufferbeam by 007 Gang junior volunteer
Luke Perry.
Photograph: Darrin Crone.
5 August 2017 |
The left hand water valve with the feed pipe from the tender sump are still connected in this
photo. The valve will be separated from the pipework and will be refurbished.
Photograph: Darrin Crone.
5 August 2017 |
The lower bearing faces on the bogie centre casting have been polished and on this face three
new bearing plate securing screws have been fitted, one at the bottom left of the photo and two,
one either side of the second from the top circular oilway.
Photograph: Darrin Crone.
5 August 2017 |
The refurbished cylinder lubricator, furthest from the camera has been refitted.
Photograph: Darrin Crone.
5 August 2017 |
The lubricator pipework from the cylinder lubricator has been refurbished and refitted.
Photograph: Darrin Crone.
5 August 2017 |
The new sandbox studs have been fitted to the frames and the frames painted. The sandbox can now
be refitted.
Photograph: Darrin Crone.
5 August 2017 |
The trailing bogie wheel splashers are fastened to the loco main frames under the leading
sandboxes. They have been repaired this week and are receiving a coat of primer applied by
Engineering Team volunteer Anne-Marie Lawn.
Photograph: Peter Brackstone.
10 August 2017 |
At Llangollen progress continues with the repair of the combustion chamber platework and the
completion of the removal of the sling stays. The holes in the firebox roof plate can be seen along
with the leading horizontal transverse stay.
Photograph: Paul Aston.
10 August 2017 |
When the new valve liners are put in the steam chests they will be held in place by screws
passing through the clamp plates made this week.
Photograph: Darrin Crone.
12 August 2017 |
To position the liners accurately they can be turned in the steam chest by the special tool made
this week. It is important that their radial position is accurately located so that the gaps in the
valve rings run over the bridges between the ports and not over the port openings.
Photograph: Darrin Crone.
12 August 2017 |
New studs for the right hand leading sandbox trial fitted.
Photograph: Darrin Crone.
12 August 2017 |
The left hand leading sandbox in place. It's a tight squeeze to get the sandbox in between
the cylinder casting and slidebar bracket and to get the top through the hole in the footplate.
Photograph: Darrin Crone.
12 August 2017 |
The sump from the tender stood on end after removal this week.
Photograph: Darrin Crone.
12 August 2017 |
Engineering Team Leader Bob Shearman gives the valve liners a thorough inspection prior to their
fitting.
Photograph: Ken Woods.
15 August 2017 |
Bob Shearman and Mike Page from the engineering team taking a final look at the new valve liners
before they are fitted, planned for the next day.
Photograph: Trevor Camp/SNGLT.
16 August 2017 |
One of the Multi-Tech Engineering fitters lifts the right leading valve liner in to position.
The liner is cooled to approximately -200C.
Photograph: Trevor Camp/SNGLT.
17 August 2017 |
With cooled nitrogen evaporating from the surface the first of the new valve liners is put into
place by the specialist contractors this morning. To fit the liners into the valves, they were
contracted by cooling with liquid nitrogen which ensured a tight fit when they expanded back to
normal temperature.
Photograph: Trevor Camp/SNGLT.
17 August 2017 |
Darrin Crone (right) looks on as the first of the new valve
liners is successfully refitted.
Photograph: Trevor Camp/SNGLT.
17 August 2017 |
The right trailing valve liner in position shortly after fitting. It is still cold enough to
freeze condensation on its surface. The liner is held securely in place with clamps and at the
bottom of the liner a notch can be seen in the front face. This is to allow accurate alignment
against marks on the steam chest casting.
Photograph: Darrin Crone.
17 August 2017 |
As soon as the liners were fitted and their location checked the right hand leading sandbox was
mounted on the frames.
Photograph: Darrin Crone.
17 August 2017 |
The upturned sump from the tender after descaling. A hole was found near the bottom flange, at
about the 4 o'clock position in the photograph.
Photograph: Darrin Crone.
17 August 2017 |
A view of one of the tender tank brackets. The outside of the tank is at the top of the photo
and the frames towards the bottom. The nuts have been removed from the 2 bolts holding the tank
down.
Photograph: Darrin Crone.
17 August 2017 |
Not mentioned in the report but we have obtained a new spiral spring for the reversing shaft as
the original, furthest from the camera, was broken. The new spring requires work to fit the
existing mounting bolt. This work is well advanced.
Photograph: Darrin Crone.
17 August 2017 |
Work progresses on the superheater at the works of K D Flavell. The top flange that the
anti-vacuum valve has now been welded in position and is being skimmed.
Photograph: Darrin Crone.
18 August 2017 |
Also at the works of K D Flavell are the loco leading brake cylinders for the refurbishment of
the mounting trunnions. The photograph shows a trunnion that has been skimmed to return it to round
with its sleeve in front. The sleeve will be heated and slid on. When cooled in position it will be
an interference fit.
Photograph: Darrin Crone.
18 August 2017 |
At Llangollen, a view of the new section of right hand outer wrapper, looking forward. A few
trial copper stays are in place.
Photograph: Richard Swales.
24 August 2017 |
A view from inside the firebox showing the combustion chamber, where work continues on repairs
prior to fitting the new tubeplate.
Photograph: Richard Swales.
24 August 2017 |
The repaired brake application handle. As good as new thanks to one of our volunteer's
patient efforts
Photograph: Darrin Crone.
2 September 2017 |
Not mentioned in the report but our new loco spring hanger bolts are now being delivered. This
is the first eight.
Photograph: Darrin Crone.
2 September 2017 |
The spiral spring that counterbalances the weight of the reversing gear has a cut out made to
fit its mounting bolt and pin.
Photograph: Darrin Crone.
2 September 2017 |
Bolts holding the tender tank on to the frames go all around the tender at footplate level.
Those across the vestibule are counter sunk and needed their heads removing to free the tank.
Photograph: Darrin Crone.
2 September 2017 |
Across the front of the tender most of the bolts have been removed, and in this area the tank
structure was also welded to the dragbox top. The welds have now been burnt through.
Photograph: Darrin Crone.
2 September 2017 |
The regulator stuffing box has new studs and the cover fits well.
Photograph: Darrin Crone.
2 September 2017 |
Repairs to the leading brake cylinder frame stretcher have been completed and it has now been
painted.
Photograph: Darrin Crone.
2 September 2017 |
The whitemetal bearing material has been removed from the crowns of the coupled wheel axleboxes.
Photograph: Darrin Crone.
4 September 2017 |
The bogie centre casting top has been polished and the new side control bolt has been fitted.
Photograph: Darrin Crone.
6 September 2017 |
The right and middle piston valves are to be dismantled so that the valve heads can be machined
and repositioned on the valve spindles to match the position of the ports in the new valve liners.
A start has been made by moving them in to a location where they can be more easily worked on. The
split pins against the valve head nuts have been removed.
Photograph: Richard Swales.
9 September 2017 |
There are three circular bearing plates that sit on the top of the bogie. These have been
cleaned and inspected for damage and wear. It has been decided that these discs will require
replacement.
Photograph: Darrin Crone.
9 September 2017 |
The bogie centre now fitted in the bogie frames. The centre sits on bronze bearing plates and
one of the side control bolts can be seen fitted. The bolt secures a beam that compresses the side
control springs.
Photograph: Darrin Crone.
9 September 2017 |
A closer view of the new left hand side control bolt. The side movement of the bogie is
controlled by the end of the bolt contacting a stop on the inside of the bogie frame plate.
Photograph: Darrin Crone.
9 September 2017 |
Some of the internal components for the new clackboxes. These components were delivered this
week.
Photograph: Darrin Crone.
9 September 2017 |
With the help of the 007 Gang of junior volunteers two new bolts were fitted to the operating
arm of the regulator valve.
Photograph: Darrin Crone.
9 September 2017 |
The electrical frame removed from the vestibule of the tender. The frame was partially
reassembled after being removed in parts. Some sections have been subject to corrosion and will
require refurbishment.
Photograph: Darrin Crone.
9 September 2017 |
The wheelsets return to NRM York by Archers of Northallerton. The trailer will be left here and
the rigid chassis truck will take the wheelsets round to the workshop yard.
Photograph: Trevor Camp/SNGLT.
12 September 2017 |
The last wheelset to touch the rail in the NRM workshop was the driving wheelset. The driving
wheelset is lowered on to the rail in front of 60007's frames.
Photograph: Trevor Camp/SNGLT.
12 September 2017 |
The last two fitted rivets through the spring brackets were fitted this week.
Photograph: Darrin Crone.
14 September 2017 |
Not mentioned in the report but more work has been done in preparing the spring hanger holes in
the coupled wheel springs.
Photograph: Darrin Crone.
14 September 2017 |
The left hand side mainframe plate has been painted to top coat between the cylinder and
Cartazzi frames.
Photograph: Darrin Crone.
14 September 2017 |
The boiler side stays being machined on the CNC lathe at Llangollen.
Photograph: Paul Aston.
14 September 2017 |
The bogie wheelsets are the first to be measured. The measurements taken are to enable the
axleboxes to be made to suit.
Photograph: Richard Swales.
16 September 2017 |
A view of the returned wheelsets over the wheeldrop in the NRM workshop, with 60007's frames
behind.
Photograph: Richard Swales.
16 September 2017 |
The leading loco brake cylinders were returned to the NRM workshop this week from contractor
repair at K D Flavell. The outside bearings are being tried on for size. Their fit is good but the
bearing surfaces are corroded so they will have to be replaced.
Photograph: Richard Swales.
16 September 2017 |
The alignment wire being set up on the left hand engine. The wire is centred at the front of the
cylinder bore and is stretched tight toward the rear of the mainframes, theoretically through the
centre of the driving wheel axle.
Photograph: Richard Swales.
16 September 2017 |
The spiral spring just started on the reversing shaft. It has been slid up wedges either side of
the square on the end of the shaft. It is a very tight fit.
Photograph: Andy Barwick.
19 September 2017 |
The alignment wire has been put up on the left side of the engine as described last week. It has
paper tags put on to make sure it isn't accidentally disturbed.
Photograph: Darrin Crone.
21 September 2017 |
The lower front streamlining and buffers were refitted this week.
Photograph: Darrin Crone.
21 September 2017 |
The wheelsets have taken a lot of work to get them looking this good.
Photograph: Darrin Crone.
21 September 2017 |
The vacuum tank from the tender that is mounted between the frames just behind the bufferbeam.
This part of the tender is packed with drawgear components and pipework. Some of this will be
removed to ensure no parts could foul the lifting of the tank.
Photograph: Darrin Crone.
21 September 2017 |
Two of the clackbox castings that that have failed pressure testing. They will be melted down
and recast. It is not unusual to have castings fail like this when the foundry is dealing with
unusual and small batches.
Photograph: Darrin Crone.
22 September 2017 |
The valves and clack cap for the left hand clackbox were taken to the machine shop where the
clackbox bodies will be machined. The clackboxes need these parts fitting for final pressure
testing.
Photograph: Darrin Crone.
28 September 2017 |
The tender tank is now lifted from the frames and stands off the frames on a couple of inches of
packing. The gangway bellow assembly lays on its side ties to the buffer stops in the NRM
workshop.
Photograph: Darrin Crone.
28 September 2017 |
The refurbished coach air brake cylinders were returned to York this week.
Photograph: Darrin Crone.
28 September 2017 |
Packing can be seen below the tank in this photo of the rear bufferbeam area. The square section
bars with bolts in their ends support the gangway connection and are spring loaded to push the
connection out.
Photograph: Darrin Crone.
28 September 2017 |
Just part of the pipework being worked on at the moment. This is a collection of loco vacuum
brake and steam heat pipework.
Photograph: Darrin Crone.
28 September 2017 |
The first paint is being applied to the returned wheelsets. This is the driving set.
Photograph: Darrin Crone.
28 September 2017 |
Not mentioned in the report, we visited the works of K D Flavell who are refurbishing the
superheater header. Here it is stood on the flange that fastens on to the boiler. The top and end
faces are complete and this visit was to agree the repair procedure of the element holes.
Photograph: Darrin Crone.
29 September 2017 |
The reversing shaft was fitted this week. The spiral spring that counteracts the wight of the
reversing assembly, and the vacuum clutch that locks the shaft in position can be seen.
Photograph: Andy Barwick.
29 September 2017 |
The leading vacuum cylinder centre bearing has had its fixing holes welded up as it is to be
repositioned on the loco and new holes will be drilled through. The bottom of the "U" has
been built up with weld and bored out to a specified diameter to suit the vacuum cylinder
trunions.
Photograph: Darrin Crone.
1 October 2017 |
The staying of the new side plates of the boiler at Llangollen is now complete. This view shows
the inside of the firebox. The area of new staying is apparent. The bottom row of stays will be put
in after the replacement of the foundation ring.
Photograph: Paul Aston.
4 October 2017 |
Steady progress is being made with the wheelsets. They have now been thoroughly cleaned of the
grease and wax put on them to protect them during their repairs and primer is now being applied.
Photograph: Peter Brackstone.
5 October 2017 |
The pegs that prevent the rotation of the rings in the valve heads have been drilled out this
week. This has to be done very carefully and requires accurate setting up to ensure no damage to
the valve head as they are to be reused.
Photograph: Darrin Crone.
5 October 2017 |
One of the valve ring pegs after drilling out.
Photograph: Darrin Crone.
5 October 2017 |
Much time and effort has been put in to cleaning and preparing pipework for refitting. This pipe
is part of the run from the steam chest to the cab. It originally controlled the exhaust steam
injector but is now used for the steam chest pressure gauge.
Photograph: Darrin Crone.
5 October 2017 |
The leading vacuum cylinder centre bearing bracket was put in its correct position this week and
the mounting holes drilled to suit. It was then removed for painting. Here it is on the painting
bench.
Photograph: Darrin Crone.
5 October 2017 |
The bottom of the tender sump was cut out this week and the flange in the plate recovered. The
flange can be seen inside. New plate will be welded in and the old flange re-used.
Photograph: Darrin Crone.
5 October 2017 |
The completed vacuum cylinder has been assembled using new seals and the piston checked to
ensure free movement. Andy Barwick appears pleased with the results of his efforts.
Photograph: Malc Bateman.
6 October 2017 |
The air brake piping has been refitted around the front bufferbeam.
Photograph: Darrin Crone.
14 October 2017 |
The steam heat pipework was refitted to the loco this week. This view shows behind the front
bufferbeam. The pipework for the steam heat still requires securing to all its brackets.
Photograph: Darrin Crone.
14 October 2017 |
The platework around the Cartazzi has been given another coat of cleaning and descaling in
preparation for final testing as repairs to the inner frames are completed in this area.
Photograph: Darrin Crone.
14 October 2017 |
The overhaul of the leading vacuum brake cylinders has been completed with only painting now to
be completed.
Photograph: Darrin Crone.
14 October 2017 |
A view from the end of the steam heat pipe at the cab end of the loco frames. The end of pipe
can be seen on the right as it snakes up the frames.
Photograph: Darrin Crone.
14 October 2017 |
The wheelsets continue to be finally cleaned and receiving coats of primer. The photo shows the
progress so far with one of the bogie wheelsets.
Photograph:Darrin Crone .
14 October 2017 |
The piston valve heads have now had all the pegs removed and are ready for machining to suit the
new valve liners.
Photograph: Darrin Crone.
14 October 2017 |
The valve heads are dye penetrant inspected by Roger Turnbull and Andrew Jacques.
Photograph: Darrin Crone.
17 October 2017 |
The bogie cladding plates being trial fitted and repaired. This work is now completed and they
are now being painted.
Photograph: Peter Brackstone.
17 October 2017 |
The results of hours of work, another coupled wheel is now ready for filling and painting.
Photograph: Peter Brackstone.
18 October 2017 |
Re-installing the refurbished pipework continues with Dave Lee and Peter Ellis working out the
best sequence for work to continue.
Photograph: Peter Brackstone.
18 October 2017 |
The boiler is put on its side at Llangollen. It was lifted on to bogies and returned to the
boiler shop. The new stays can be seen on the lower sections of the plates inside of the firebox.
Photograph: Paul Aston.
19 October 2017 |
The inner Cartazzi frames to the rear of the main frame plates and the diaphragm plate stretcher
have been repaired, inspected and "signed off". They received paint this week.
Photograph: Darrin Crone.
19 October 2017 |
The 24" vacuum brake cylinder was reassembled last week with a new rolling ring and checked
for operation by Andy Barwick. It operated satisfactorily and the cylinder is now being painted by
Andy.
Photograph: Darrin Crone.
19 October 2017 |
One of the coupled wheels is being filled prior to painting.
Photograph: Darrin Crone.
21 October 2017 |
The bogie has been raised to ease access to the hornstays which require new bolting.
Photograph: Darrin Crone.
21 October 2017 |
The ashpan is lifted and the rail wagon it was on has been rolled back out of the way.
Photograph: Andy Barwick.
27 October 2017 |
The superheater at the works of K D Flavell on the bench during examination by SNG Engineers.
Further work is required.
Photograph: Darrin Crone.
27 October 2017 |
New fitted bolts are being fitted to the bogie hornstays. One is in place and the other is
ready for fitting.
Photograph: Darrin Crone.
28 October 2017 |
The ashpan is now in the NRM workshop ready to be worked on. It will require some new platework
to return it to its original shape, and to replace wasted areas.
Photograph: Darrin Crone.
28October 2017 |
Two of the coupled wheelsets have now received filler, but there's still plenty to do.
Photograph: Darrin Crone.
28 October 2017 |
The fitting of the steam chest pressure pipe, with the yellow tag, from the smokebox to the
Cartazzi complete. The pipe in green primer is part of the vacuum brake system and this is now
being fitted.
Photograph: Darrin Crone.
28 October 2017 |
New fitted bolts being put in the leading right combined bracket. It is apparent why special
reduced diameter washers are required.
Photograph: Darrin Crone.
28 October 2017 |
The bogie hornstays have had a final inspection around the bolt holes before refitting. They
will be removed once more to allow the axleboxes to be fitted.
Photograph: Darrin Crone.
2 November 2017 |
A straight edge is clamped across the rear of one of the driving wheels so that the distance
from the centre thrust face to the tyre profile can be measured. This will give us the required
thickness of the front face of the axlebox.
Photograph: Richard Swales.
4 November 2017 |
The ashpan is now being repaired in the NRM workshop. The heated areas can be seen at the front
of the ashpan where the plates are being straightened.
Photograph: Richard Swales.
4 November 2017 |
All the coupled wheels have now seen filler and many have been finish sanded, but there's a
long way to go yet.
Photograph: Richard Swales.
4 November 2017 |
The repaired tender sump.
Photograph: Richard Swales.
4 November 2017 |
The bogie with new hornstay bolting and in front is the bogie suspension springs.
Photograph: Darrin Crone.
4 November 2017 |
Another piece of the vacuum system pipe jigsaw, refurbished with repaired ends.
Photograph: Darrin Crone.
4 November 2017 |
We now have six sound clackbox castings so we can progress to final machining.
Photograph: Darrin Crone.
10 November 2017 |
The driving wheelset is the last to get the filling and sanding treatment.
Photograph: Darrin Crone.
11 November 2017 |
The bogie rubber spring on top of the "box" it normally sits in. These are on the
bottom of the steel coil suspension springs.
Photograph: Darrin Crone.
11 November 2017 |
The wire through the left cylinder passes along the centre line. A wire is now to be put up
across the front of the loco to measure any error in the positioning of the cylinders across the
loco.
Photograph: Trevor Camp/SNGLT.
14 November 2017 |
The front of the wire can be seen in the cylinder bore. The loco is a little dusty because of
the filling and sanding that has been done over the last few weeks.
Photograph: Trevor Camp/SNGLT.
14 November 2017 |
All the fitted bolts are in the right leading combined bracket which has allowed the final two
frame rivets to be put in. With pipework now being re-installed access to the frames is getting
more difficult.
Photograph: Trevor Camp/SNGLT.
14 November 2017 |
The main task of the last few weeks has been the filling and sanding of the coupled wheels.
Photograph: Trevor Camp/SNGLT.
14 November 2017 |
The final closing of the frame rivets is done by hand by a team of two working opposite sides of
the rivet.
Photograph: Peter Brackstone.
18 November 2017 |
The last two fitted rivets have now been closed. This will allow this final part of the loco
main frames to be painted to top coat.
Photograph: Darrin Crone.
18 November 2017 |
The ashpan being moved by Engineering Team volunteers. We received the full co-operation of the
NRM Security Team as each time we wanted to use the crane the workshop gallery drawbridge had to be
operated by them.
Photograph: Peter Brackstone.
22 November 2017 |
A considerable amount of space was taken up in the NRM workshop by some old traction motors.
With the space released by the traction motors we now have a suitable space for working on the
ashpan and bogie wheels.
Photograph: Peter Brackstone.
22 November 2017 |
This week to release the space for our use we moved the old traction motors on to a lowmac
wagon. Here they are loaded.
Photograph: Peter Brackstone.
22 November 2017 |
The boiler in the works at Llangollen. It is now laid on its side. The firebox roof with the
removed stays can be seen.
Photograph: Darrin Crone.
23 November 2017 |
With most of the roof stays removed the inside of the outer doorplate can be seen from the
tubeplate end of the firebox. The pipes supply steam to the injectors.
Photograph: Darrin Crone.
23 November 2017 |
The leading vacuum cylinder centre bearing has been extensively refurbished and was refitted
this week. The overhauled pipework that has been fitted in recent weeks can be seen.
Photograph: Darrin Crone.
25 November 2017 |
The copper gaskets that seal boiler fittings have been returned to the workshop for inspection
so that we can decide if any require replacement.
Photograph: Darrin Crone.
25 November 2017 |
The blow off cock has been dismantled and cleaned this week and will be required for fitting to
the boiler at Llangollen. While repairing the valve seat it is apparent the valve will need more
work to ensure reliable operation in to the future.
Photograph: Darrin Crone.
25 November 2017 |
One of the bogie axleboxes being bored out by the NYMR workshop.
Photograph: Darrin Crone.
28 November 2017 |
The ashpan has seen further work this week with the strengthening plates removed from the lower
front as they had warped. New steelwork will be put in.
Photograph: Darrin Crone.
30 November 2017 |
The bogie wheels are now receiving undercoat.
Photograph: Darrin Crone.
30 November 2017 |
Not mentioned in the report but the repaired tender sump has been prime painted this week.
Photograph: Darrin Crone.
30 November 2017 |
The outside right loco mainframes have been painted to top coat this week.
Photograph: Peter Brackstone.
1 December 2017 |
The leading and trailing wheelsets have painted in primer this week.
Photograph: Peter Brackstone.
1 December 2017 |
The platework in the tender coal space has been examined for thickness.
Photograph: Richard Swales.
2 December 2017 |
In the centre of the photo of the rear of the loco frames the end of the steam heat pipe. This
is the first pipe run completed the full length of the loco.
Photograph: Darrin Crone.
9 December 2017 |
The superheater header has now returned to the NRM workshop at York. There is still work to be
done and pressure testing before it can join the boiler at Llangollen.
Photograph: Darrin Crone.
9 December 2017 |
The header came back with new end plugs. The plugs cover the ends of the outermost row of
elements and are removed to access the elements for expanding.
Photograph: Darrin Crone.
9 December 2017 |
The pipe connection fittings have been put on the vacuum cylinders. This is the 24"
cylinder.
Photograph: Darrin Crone.
9 December 2017 |
The coupled wheels have now received two coats of primer. After a light rub down they will be
painted in undercoat.
Photograph: Darrin Crone.
9 December 2017 |
Some of our collection of superheater element expander gear being sorted for use.
Photograph: Darrin Crone.
9 December 2017 |
One of the leading vacuum cylinder outer bearings has been weld repaired and bored out. It
awaits refitting and the alignment checked.
Photograph: Darrin Crone.
9 December 2017 |
The front steam heat valve and hose. The valve has been stripped and examined. A new seal is
required and a new hose will be fitted.
Photograph: Darrin Crone.
9 December 2017 |
Parts of the tender filter or strainer box that prevents large solids from getting in to the
boiler feed water.
Photograph: Peter Brackstone.
14 December 2017 |
The coupled wheels are now in black undercoat. They require another coat of undercoat before
glossing.
Photograph: Peter Brackstone.
14 December 2017 |
At Llangollen the boiler was turned so that welding of the copper combustion chamber plates
could continue.
Photograph: Paul Aston.
14 December 2017 |
The cylinder drain cocks are now being examined and cleaned prior to refurbishment.
Photograph: Darrin Crone.
16 December 2017 |
The brake gear is being removed from the tender. The left side pull rods that connect the lower
end of the brake hangers are laid next to the tender. They will be cleaned, stripped and
examined.
Photograph: Darrin Crone.
16 December 2017 |
Some of the cylinder drain cock linkage. It is yet to be fully assessed for condition.
Photograph: Darrin Crone.
16 December 2017 |
The LNER boiler blow off cock required internal machining so that the valve could be ground in
true.
Photograph: Darrin Crone.
24 December 2017 |
|
|