The Sir Nigel Gresley Locomotive Trust LtdSubscribe to 60007

Registered Charity Nº1079591


Number 7's Photograph Gallery

Clicking on the images will display a larger version.
Clicking again will close the window. Where an 'X' shows bottom right of the image, click on this (or use the 'f' key) to display full size.
(You may wish to maximise your screen for this)


We do receive a number of photos that have no caption provided. Please note that if there is no caption then the photo won't be used.


Sir Nigel Gresley is now out of traffic for overhaul. This will probably take three years and cost about £750,000. If you would like to make a donation towards this overhaul please click on one of the the donate buttons.


To donate via PayPal (incl. credit or debit card):Donate         To donate by 'phone: Donate


A progress report for the overhaul may be found here.
 


From Overhaul January 2018

Painting team leader Peter Brackstone applies the first coat of gloss to the coupled wheels.
Photograph: T Camp/SNGLT.

4 January 2018

The trailing coupled wheelset make a fine sight with a complete first coat of gloss.
Photograph: T Camp/SNGLT.

4 January 2018

At Llangollen the firebox crown plate has been lowered at the tubeplate end and a template of the new tubeplate tried in place.
Photograph: Paul Aston.

4 January 2018

The injectors and damper cross shaft have been fitted to allow the accurate positioning of the pipework beneath the cab.
Photograph: Darrin Crone.

6 January 2018

New bushes are being fitted to the drain cock valves to mininise steam leakage around the valve spindles. Two of the old bushes are in the foreground.
Photograph: Darrin Crone.

6 January 2018

The boiler blanking plates will be fitted to the boiler during testing to close up the holes where the boiler fittings are located.
Photograph: Darrin Crone.

6 January 2018

The middle upper slide bar on the forklift on its way to be measured for flatness of the surface the crosshead runs against.
Photograph: Darrin Crone.

13 January 2018

The studs have been removed from the superheater face where the middle steam pipe connects. This will allow the full face to be repaired and dressed.
Photograph: Darrin Crone.

13 January 2018

The cylinder drain cocks have two integral valves. An automatic pressure relief valve and a poppet valve operated by the driver to allow the cylinders to be drained. Both parts of the six valve units have now been overhauled.
Photograph: Darrin Crone.

13 January 2018

The coupled wheels have now received two coats of black gloss. Nearly there just the varnishing to be done.
Photograph: Darrin Crone.

13 January 2018

The coupling rods now next to the engine. There overhaul has started.
Photograph: Darrin Crone.

13 January 2018

The cab floor plate extends the full width of the loco with its outer edges forming the footplating outside the cabsides.
Photograph: Darrin Crone.

13 January 2018

The boiler is now on its back to allow work on the roof plate in the combustion chamber. The boiler was taken in to the yard at Llangollen and when turned returned to the workshop.
Photograph: Paul Aston.

19 January 2018

The cylinder drain cocks have been refitted temporarily to the outside cylinders to allow the operating linkage to be located and examined for fit.
Photograph: Darrin Crone.

20 January 2018

The superheater header middle front plate is in front of the header. The face that seals against the header has been thoroughly cleaned off and examined.
Photograph: Darrin Crone.

20 January 2018

The lower surface of the cab floor plate cleaned and now with a coat of undercoat.
Photograph: Darrin Crone.

20 January 2018

The floor plate sits across the rear of the loco frames so the painting of this area has also been carried out so that it can be fitted.
Photograph: Darrin Crone.

20 January 2018

The first two new valve heads have been delivered to the NRM for inspection and they are very good. When we receive the final two all will have the centre key ways cut in them.
Photograph: Darrin Crone.

20 January 2018

The bogie wheels are finished in gloss and are receiving a bit of tidy up around their edges. They are yet to be varnished.
Photograph: Darrin Crone.

20 January 2018

The bogie axle boxes were delivered last week and I overlooked including a photo of them. Here they are on the pallet in the NRM workshop.
Photograph: Darrin Crone.

20 January 2018

The clackboxes are being machined by TT Elecmech of Darlington. One of the castings is on the lathe having the valve threads cut.
Photograph: Tom Jones.

24 January 2018

New plate in the front left of the ashpan.
Photograph: Darrin Crone.

27 January 2018

The crankpin bushes were pressed out of the coupling rods this week and the rods are shown set up for measurement.
Photograph: Darrin Crone.

27 January 2018

The leading right coupling rod bush. The key stops the bush from rotating in the rod and the oily felt controls the flow of lubricating oil to the crackpin. The ring is fitted between the rod and the wheel to provide a side thrust bearing face.
Photograph: Darrin Crone.

27 January 2018

The dragbox area of the loco is receiving further coats of paint before the floor plate is fitted and prevents further access.
Photograph: Darrin Crone.

27 January 2018

The superheater header element holes are being reamed to take out ovality and taper.
Photograph: Darrin Crone.

27 January 2018

The brake gear removal from the tender continues.
Photograph: Darrin Crone.

27 January 2018

The GSMR equipment is mounted on a rack fitted in the tender corridor vestibule. It has been dismantled and is being repaired and prepared for repainting.
Photograph: Darrin Crone.

27 January 2018

The clackboxes at the works of TT Elecmech where they are being machined. The reconditioned valves are fitted to the clackbox castings to check fit and allow an intermediate pressure test.
Photograph: Darrin Crone.

29 January 2018

At Llangollen the new firebox tubeplate is being marked for its flange to be drilled prior to fitting.
Photograph: Paul Aston.

1 February 2018

The regulator cross shaft and stuffing box have been trial mounted on the backhead of the boiler.
Photograph: Paul Aston.

1 February 2018

The right side coupling rods have had their bushes pressed out and are being examined for defects.
Photograph: Darrin Crone.

3 February 2018

The platework that stands on the cab floorplate and supports the wooden floor. The green primer painted plate can be reused, the plates beyond require replacement.
Photograph: Darrin Crone.

3 February 2018

The left outside connecting rod has had its bushes removed and is measured. The rod projecting from the big end bearing hole allows a long internal micrometer to be used to check the bearing centres.
Photograph: Darrin Crone.

3 February 2018

The six lower slidebars have been on the surface table in the NRM Workshop and been measured for wear.
Photograph: Darrin Crone.

3 February 2018

The reaming of the superheater element holes continues.
Photograph: Darrin Crone.

3 February 2018

The bogie wheelsets have been moved back on to the rail in front of the loco.
Photograph: Darrin Crone.

3 February 2018

The inspection of the coupling rods has continued with the ends inspected for cracks.
Photograph: Darrin Crone.

6 February 2018

The tender coal space and the top of the corridor is being descaled. A large amount of material has been removed.
Photograph: Darrin Crone.

6 February 2018

The little end, or gudgeon pins have been thoroughly prepared for examination. They have now been measured for wear.
Photograph: Darrin Crone.

6 February 2018

The tyre edges on the bogie wheels have been cleaned off, the trailing set has been turned round to get it the right way round and the protective covers removed from the journals. The wheelsets sit on the NRM workshop wheel drop, originally part of York North depot.
Photograph: Darrin Crone.

6 February 2018

The ashpan back right back corner has received further new plate.
Photograph: Darrin Crone.

6 February 2018

The inside connecting rod has been retrieved from store, cleaned up and a start made on measuring it as part of its examination.
Photograph: Darrin Crone.

6 February 2018

The clamp that pulls the regulator valve on to the internal steam pipe inside of the the boiler barrel was retrieved from store this week and prepared to be sent to Llangollen.
Photograph: Darrin Crone.

6 February 2018

At Llangollen work progresses on the tube plate and the regulator set up. This photo shows inside the stuffing box on the backhead with the reach rod that goes through the boiler to the regulator valve.
Photograph: Paul Aston.

7 February 2018

The floor plate is lowered in to position by Roger Turnbull and Ian Seales.
Photograph: Malc Bateman.

8 February 2018

The rear cab upstand is lowered in to position.
Photograph: Trevor Camp/SNGLT.

14 February 2018

The bogie wheel journals and thrust faces are polished to a high standard before fitting the axleboxes. The wheelsets sit on the NRM workshops wheeldrop.
Photograph: Peter Brackstone.

15 February 2018

The bogie axleboxes are in the process of being fitted. Andy Lowes puts in the oil wedges on the left side boxes.
Photograph: Richard Swales.

17 February 2018

The outside upper slidebars have been inspected for possible cracking around their mounting holes. No defects have been found.
Photograph: Darrin Crone.

17 February 2018

The right side bogie axleboxes have been fitted and are put to one side.
Photograph: Malc Bateman.

17 February 2018

Not mentioned in the report but measuring the moving parts of the locomotive continues. Here the inside connecting rod receives the attention of the Chief Mechanical Engineers micrometers.
Photograph: Darrin Crone.

17 February 2018

The rubber springs for the bogie and coupled wheels were assembled this week. Supplied as separate steel and rubber plates they are glued together with a high strength two part adhesive.
Photograph: Darrin Crone.

17 February 2018

The upper middle slidebar is inspected for defects around its mounting holes. All the slidebars are inspected like this before refitting. They have also been measured for wear.
Photograph: Darrin Crone.

20 February 2018

A new section of platework has been let in to the fireman's side cab floor support to replace wasted plate.
Photograph: Peter Brackstone.

21 February 2018

The superheater header refurbishment continued this week with the reamed element holes deburred.
Photograph: Darrin Crone.

22 February 2018

The cylinder relief valves are dismantled, cleaned, inspected and refurbished. The parts of each valve being kept together.
Photograph: Darrin Crone.

22 February 2018

The cylinder drain operating linkages have been refurbished and is being trial fitted.
Photograph: Darrin Crone.

22 February 2018

Now that the cab floor plate is fitted pipework begins to emerge.
Photograph: Darrin Crone.

22 February 2018

The new copper tubeplate is now in position, in the upturned boiler.
Photograph: Paul Aston.

22 February 2018

The left piston crosshead has been inspected for damage and defects. No faults were found.
Photograph: Darrin Crone.

3 March 2018

The cylinder relief valves have been overhauled.
Photograph: Darrin Crone.

3 March 2018

The left upper sidebar has been accurately positioned.
Photograph: Darrin Crone.

3 March 2018

The cab floor structure is in position, though more fitting is required.
Photograph: Darrin Crone.

3 March 2018

Safety valve components are on the surface table being inspected and measured.
Photograph: Darrin Crone.

3 March 2018

The combined timing reservoir is mounted to the leading transverse cab floor upstand. A view looking toward the driver's side. Primed plates are existing plate, unpainted plate is new.
Photograph: Darrin Crone.

10 March 2018

The large heavy casting that is the main part of the reverser stand. Laid on its back it normally stands on the base in the front of the photograph. Here most of the paint has been removed prior to testing for defects.
Photograph: Darrin Crone.

10 March 2018

The reverser stand and the screw that operates the reversing links and gear, that is normally down the middle of the stand.
Photograph: Darrin Crone.

10 March 2018

The right upper slide bar is in position and aligned with the wire from the cylinder centre line.
Photograph: Darrin Crone.

10 March 2018

A section of the outer layer of the tender corridor roof has been removed. Over the top the end of the streamlining can be seen where a section has been cut away. The streamlining was added to the original 1928 tender when it was transferred to A4 use. Under the streamlining is the original beading that marks the top of the 1928 tender.
Photograph: Darrin Crone.

10 March 2018

The tender brakeshaft is being stripped and descaled for inspection. It is seen here with its end brackets in place. It is mounted at the front of the tender frames.
Photograph: Darrin Crone.

10 March 2018

The drain cock cab Bowden pulley, marked for sands but so is the sands one.
Photograph: Darrin Crone.

17 March 2018

A view looking toward the front right of the tender with a section of tender corridor removed. On the outside the A4 fairing has also been removed. The beading which was the top of the original 1928 tender can be seen.
Photograph: Darrin Crone.

17 March 2018

The gap between the middle cylinder alignment wire and middle upper slidebar is measured with a micrometer by Chief Mechanical Engineer Richard Swales.
Photograph: Darrin Crone.

17 March 2018

The loco brake hangers are being rebuilt with weld where the cast iron brake blocks rub and wear away the hanger.
Photograph: Darrin Crone.

17 March 2018

The air brake components have been returned from contractor overhaul and are being positioned under the cab floor. The nearest valve is the FVF2, but it's bigger than the old unit so won't fit in the same place.
Photograph: Darrin Crone.

17 March 2018

The piston rod taper jig in place in the right crosshead.
Photograph: Richard Swales.

24 March 2018

The removal of the corridor plate work from the tender is ongoing.
Photograph: Peter Brackstone.

28 March 2018

The reverser column has been cleaned tested and prime painted.
Photograph: Peter Brackstone.

28 March 2018

A view of the tubeplate from the firebox side.
Photograph: Richard Swales.

29 March 2018

Our CME closely inspects every inch of the tubeplate joint inside the boiler at Llangollen.
Photograph: Darrin Crone.

29 March 2018

The bogie frames, wheelsets and suspension components brought together for assembly, if only we could get close enough to put them together but the painting team won't let us anywhere near them during varnishing.
Photograph: Darrin Crone.

7 April 2018

The middle crosshead is thoroughly cleaned prior to examination for defects and measurement of piston rod taper centre from bearing surfaces.
Photograph: Darrin Crone.

7 April 2018

The middle crosshead is inspected for defects and cracks.
Photograph: Richard Swales.

12 April 2018

The horizontal hornstay bolt holes are reamed. Accuracy and care is needed as the minimum material must be removed. Tony Bickerstaffe operates the magdrill assisted by Roger Turnbull.
Photograph: Richard Swales.

12 April 2018

.
Photograph: Darrin Crone.

14 April 2018

.
Photograph: Darrin Crone.

14 April 2018

The cast bronze discs that fit between the bogie and the loco. They are 26 ½" diameter.
Photograph: T. Crone.

16 April 2018

The coach was shunted in the NRM's North Yard so that the DB loco could come straight on to the coach.
Photograph: Darrin Crone.

17 April 2018

Not mentioned in the report the reverser reach rod di-pen inspection was completed this week.
Photograph: Darrin Crone.

18 April 2018

In the early evening the DB 66 is seen coupled to the coach ready to leave for the short trip over the network to the Holgate Engineering Works.
Photograph: Malcolm Bateman/Trevor Camp/SNGLT.

18 April 2018

At the Holgate Engineering Works the coach is winched on to the low loader.
Photograph: Peter Brackstone.

19 April 2018

At Cranmore the coach is winched off the low loader.
Photograph: Nigel Wilson.

20 April 2018

Overhaul Photographs:
September 2015 to June 2016
July to December 2016
February to June 2017
July to December 2017


Photographs of 60007 in LNER/BR service and in preservation:
LNER/BR
from 1966 to 1999
from 2006 to 2008
from 2009 and 2010
from 2011 to 2013
from 2014 and 2015


All photographs are copyright of the photographer named on the larger version.

Return to top

Page updated on Monday, 23 April 2018   Visitor Counter

Copyright © The Sir Nigel Gresley Locomotive Trust Ltd